小弟在外读书, 做的是英国电力市场。 导师有些数据, 我没有弄明白。 8 p$ T* `4 m* U 2 y* n" ^0 D: A. t$ [+ V+ H一个是; _# S! N) \" c' v2 N" l
Capital recovery factor 4 T# V! U9 I8 ?6 t9 R这个找到的中文貌似是资本回收因数, 不是太懂。; ` m+ O3 S' k1 G% M. e D w
3 U4 ^% Q( T3 d8 l1 f1 p, y( e小弟用Power Facotry 模拟出来一些结果。。。麻烦各位大大看看。。。4 N8 k- G/ j8 z/ r4 o
% S3 }& A' H& x: @) F! e4 B3 P. o
| System Average Interruption Frequency Index : SAIFI: = 1.601094 1/Ca |: h) }9 A" g4 ?
| Customer Average Interruption Frequency Index : CAIFI: = 1.601094 1/Ca |2 M$ t6 f& M7 {8 K
| System Average Interruption Duration Index : SAIDI: = 193.368 h/Ca | 3 {& @* t' |/ m" g" e5 m, {8 Y| Customer Average Interruption Duration Index : CAIDI: = 120.772 h | 3 S/ _. m% B5 c* L c: d| Average Service Availability Index : ASAI: = 0.9779260217 |7 [$ s; g5 L, U0 W9 j
| Average Service Unavailability Index : ASUI: = 0.0220739783 | f+ W2 ]$ @" V6 j| Energy Not Supplied : ENS: = 3867.361 MWh/a | ; ~5 X2 V1 v2 p6 n9 \| Average Energy Not Supplied : AENS: = 3867.361 MWh/Ca |* ]! ]/ p: q/ u, H0 X1 n
| Average Customer Curtailment Index : ACCI: = 2495.645 MWh/Ca |' a2 {, z* D9 y+ r
1 {- |& t/ r% N h3 M! D然后导师跟我说。。。0 G3 L, ~6 S$ `$ o
计算公式。。。 4 r) k# ~9 ?! z6 e# E+ _* h没听太明白。。。: B- l/ }, |0 Z O' m/ d, o* ~6 D
* p8 Q( |7 p8 T+ {" q* ]3 t0 z
Curtailment cost to system operator! W$ `- m3 m$ M; o8 l
= WindFarm size * load factor * depended Number of Hours with on connection * (offer price - bid price) ' r3 ~9 w' u" @ S n b8 q! `5 v) b9 s5 _
我在书上查说, 算COST应该是用Average Service Unavailability Index ... 4 a! \) Q5 P5 _; k" Z" d" x但为啥没有用? ' X* A. u. O8 q8 Y3 @8 E$ k* L, O : l) ?8 v5 P( h* i他提到貌似这里面有个要用到上面的参数。。。 " ^9 C' u" S' @- a; d, e5 l5 u3 ^完全不懂。。。; T2 p# G0 D( G$ C* r1 W' _
查了很多资料, 没找到。。。: r* `( F3 _2 q0 Z4 |1 r, _
麻烦大家了